Some of the building needed to be re-clad, but as a viable and cost effective alternative, they opted to renovate the existing cladding for a large portion of the building. The project was phased into 2 parts – completing the prepping and interior painting of 800m2 of steel work and 1500m2 of cladding spraying to the metal clad ceilings and walls in November 2014. Then to have the weather on our side, we complete the external cladding renovation of 1200m2 of the exterior in March 2015. Throughout the project, the building was occupied and we worked around a number of other trades – often working out of hours at the weekend to make this easier.